Assignment:

Finish the table and draw and label the CPM chart. Show the critical path.

 
Activity    
Estimated
Duration   
 
EST      
 
EFT      
 
LST      
 
LFT      
 
Slack      
1,2 4 days          
2,3 5 days          
3,4 2 days          
3,5 3 days          
4,6 6 days          
5,6 2 days          
6,14 7 days          
2,7 6 days          
7,8 8 days          
8,14 2 days          
1,9 5 days          
9,10 3 days          
9,12 9 days          
10,11 4 days          
11,13 1 day          
12,13 2 days          
13,14 6 days